Puhoi to Warkworth Works Update

Dear Neighbour,

I hope this email finds you safe and well, we acknowledge that although we are not 100% back to normal yet, level 2 is just around the corner and hopefully things keep heading in a positive direction. 

Work is progressing well on the Okahu and Pūhoi viaducts and you can already see them taking shape. There is however more work to complete, there are a few separate scope of works happening over the next few months on or near Pūhoi Road. I’d like to update you on what works we have coming up. These works include:

  • Pūhoi Road night works/road closure – 24-26 May
  • Pūhoi Viaduct – girder and deck panel installation / concrete pours
  • Pūhoi Road – off-ramp earthworks and sealing
  • Pūhoi road (intersection) widening, earthworks and culvert installation
  • Southern connection works, by the tunnels – road layout changes

Most of this work will happen during the day and may not affect some of you at all, although there will be increased truck movement on SH1 and Pūhoi Road intersection.  For everyone’s safety some of the work is required to be done at night when traffic volumes are lower. Some work will require temporary night time road closures and others will require stop/go traffic management. I will advise you before each of these works are scheduled to start, with additional details. 

As there will be heavy vehicles and machinery operating in the area, we do ask that you please ensure you follow the construction and temporary traffic management signs. These measures have been put in place to protect the safety of the community and work crews.

We thank you for your understanding while we complete this important work.

Please don’t hesitate to contact us if you have any questions or concerns.

Noho ora mai/Stay safe,

Roslyn Prictor

NX2 Stakeholder and Communications Team

P. 0508 P2WK INFO (0508 7295 4636)  E. info@nx2group.com         W. nx2group.com

A. 45 Wyllie Road, Warkworth   P.  P.O Box 690, Warkworth 0941

cid:image001.png@01D2A3ED.EBCC5820