NX2: Busy Summer Sundays

With summer just around the corner and bulk earthworks starting to kick off, it is important that the Ara Tūhono – Pūhoi to Warkworth Project utilise our time and resources wisely. This includes making the most of the increased daylight hours and warmer weather. To do this we are planning to work extended hours in some areas of the project and will also be working on Sunday’s, weather permitting. 

From Sunday 13 September 2020, we will be carrying out intermittent Sunday works at various locations from Johnstones Hill Tunnel (Southern Connection) and Tapuwae o Kahumatamomoe (Moir Hill Road bridge). The projects working hours on Sundays will typically take place between 7:30am and 6:00pm, and will continue until the end of the 2020/21 summer earthworks season.

Some of you may notice noise and vibration during these works, however the project team will actively monitor this and every effort will be made to minimise disruptions. The Sunday works will be designed to comply with Auckland Council requirements for noise and vibration and our Environmental Team will be monitoring this.

If you have any questions or concerns, please don’t hesitate to get in touch.

Ngā mihi 

Roslyn Prictor

NX2 Stakeholder and Communications Team

P. 0508 P2WK INFO (0508 7295 4636)  E. info@nx2group.com         W. nx2group.com